11.20.09

CAPITAL PROJECTS

The school learning environment is a key component to student achievement.  In our district, we're committed to providing school facilities that are safe, modern and attractive. Currently, we are undergoing a four-year capital improvement plan that began in 2007.  The plan includes the following upgrades:

PHASE 1A - COMPLETED IN 2007:

Replacement of boilers & cooling tower - BHS
Alterations to kitchen - BHS
Pool dehumidification - East Middle 

PHASE 2 - 2008-2010

Window replacement - East
Auditorium renovations - Franklin
Exterior door replacement - Franklin
Site work - Coolidge
Interior renovations - Coolidge

PHASE 1B - BEGINS SUMMER, 2008:

Technology upgrades districtwide
SMARTBoard installation in classrooms
Wiring/power upgrades
Installation of wireless network
New server & storage area network

PHASE 3 - 2009-2010

Ventilation upgrades - Jefferson
Student restroom reconstruction - Wilson & Jefferson
Plumbing upgrades - Mann, Wilson, Roosevelt
Exterior door replacement - Roosevelt
Auditorium upgrades - Wilson

PHASE 1C - SPRING/SUMMER 2009

Pool restoration - BHS
Window replacement - BHS
Parking garage & play deck renovations - BHS
Repoint brick & stonework - West
Interior plaster renovation - West
Field house upgrades - West